The Power Division has reported progress on restoring electricity in flood-hit areas as of September 1. In PESCO regions including Swat, Banar, Shangla, Swabi, and DI Khan, 12 grids and 91 feeders were affected, with full restoration expected within a week. GEPCO had 10 grids and 87 feeders impacted, of which 80 are restored and 7 partially restored. In LESCO areas like Lahore, Okara, Sheikhupura, Kasur, and Nankana, 57 of 59 feeders are partially restored, with complete restoration expected by September 5. FESCO faced damage to 26 grids and 73 feeders across multiple districts, with 1 feeder fully and 72 temporarily restored. MEPCO temporarily restored 114 feeders, while permanent work will begin once floodwaters recede. In TESCO’s North Waziristan and Khyber areas, 10 feeders were affected, with 1 fully and 4 temporarily restored.